Hydroelectric
Central Hidrolectrica Providencia
Company Name
Hidromaule S.A.
Project Location
Region: VII - Maule
District: San Clemente
Contact
Jose Manuel Contardo
Phone
56-2-2453600
Technical Specifications
Total installed capacity
10,4 MW
Plant factor
68%
Grid connection point
SE Maule
Annual energy production (GWh)
62 GWh
Year of connection to grid
2011
Expected annual CO2 emission reduction amount
24800 Ton CO2 eq/year
Intended Project life
40 Years
Project Maturity
Stage
Completed
In Progress
Pending
Preinvestment Review
Technical or Finance Prefeasibility Review
Technical or Finance Feasibility Review
Basic Engineering
Detail Engineering
Construction
Operation
CERs Generation
Permits
Approved EIA or EIS
No
DNA (CONAMA) Letter of Approval
No
All appropiate construction permits
No
Completed PDD
No
Submitted for Executive Board approval
No
Legal Aspects
Secured Water Rights
Yes
Rights for electricity generating use
Yes
Power generating concession
No
Energy sales contract
No
Financing Spectations
Own financing
30%
Third-party financing
0%
Banking sources
70%
The company needs to finance Project development
Yes
The Company wants to sell the Project
No
The Company intends to sell CERs
Yes